Skip to main content

PUC Case No. 21-0881-INV - Workshop - regarding jurisdiction over Green Mountain Power Corporation's Dams

RE: Workshop Investigation regarding jurisdiction over Green Mountain Power Corporation's Dams to discuss

(1) the appropriate criteria to investigate for each dam,
(2) the work required to gather the information needed for FERC to make its determinations,
and
(3) the timeframe GMP would need to complete the work.
The initial order scheduling this workshop proposed that it be held on May 27, 2021. However, due to scheduling conflicts, the Commission has moved the date to June 3, 2021.

Before: Public Utility Commission Staff


Location: via Go To Meeting videoconference. The workshop will be recorded by a court reporter and will be open to the public.


Participants and members of the public may access the workshop online at https://global.gotomeeting.com/join/515692533, or call in by telephone using the following information: phone number: +1 (571) 317-3116; access code: 515-692-533. Participants may wish to download the GoToMeeting software application in advance of the hearing at https://global.gotomeeting.com/install/515692533 Guidance on how to join the meeting and system requirements may be found at https://www.gotomeeting.com//online-meeting-support.

Event Date