Order Requesting Comments on Requests to Extend Commissioning Deadlines

On January 18, 2022, Renewable Energy Vermont (“REV”) filed a request that the Vermont Public Utility Commission (“Commission”) grant a one-year extension of all commissioning deadlines for net-metering and standard-offer projects whose commissioning deadlines fall on or after January 1, 2022, through December 31, 2022. On January 19, 2022, AllEarth Renewables, Inc. (“AllEarth”) filed a similar extension request. The Commission is treating REV’s and AllEarth’s filings as motions. In an order issued on 02/01/2022, the Commission asks that any responses to REV’s and AllEarth’s motions be filed as public comments by February 11, 2022 in Case No. 20-0789-INV in ePUC.